System Test Plan
Table of Contents
- Introduction
- Objectives
- Scope
- Test Strategy
- Test Plan
- Test Environment
- Test Criteria
- Test Deliverables
- Test Schedule
- Resources
- Roles and Responsibilities
- Defect Management
- Risk Management
- Communication Plan
- Approval
Introduction
The purpose of this document is to provide a comprehensive system test plan for the Art App project. The Art App aims to create a mobile application that allows users to generate cute turtles in various environments, choose colors, backgrounds, shapes, and emojis, chat with other artists, earn money for creating turtles, share artwork on social media, and protect their creations from unauthorized copying.
Objectives
The primary objectives of the system testing are:
- To validate that the application meets the specified requirements.
- To ensure that the app functions correctly across different devices and platforms.
- To identify and fix any defects in the application.
- To guarantee a smooth and user-friendly experience for end-users.
Scope
The scope of system testing includes:
- Color, background, shape, and emoji customization of turtle characters.
- Chat feature for communication between artists.
- Payment feature for creating cute turtles.
- Social media sharing functionality.
- Protection against unauthorized copying of artwork.
Test Strategy
The test strategy for the Art App includes:
- Functional Testing: To verify that each feature works as expected.
- Usability Testing: To ensure the app is user-friendly.
- Performance Testing: To check the app's performance under load.
- Security Testing: To verify the app's protection mechanisms for artwork.
- Compatibility Testing: To ensure the app functions correctly on various devices and OS versions.
Test Plan
Test Environment
The testing will be conducted in the following environment:
- Devices: iOS and Android smartphones and tablets.
- Software: Latest versions of iOS and Android operating systems.
- Network: Wi-Fi and mobile data connections.
- Tools: Appium for automated testing, JIRA for defect tracking.
Test Criteria
Entry Criteria:
- All development work is completed.
- Test environment is set up.
- Test data is prepared.
- Test cases are reviewed and approved.
Exit Criteria:
- All test cases are executed.
- All critical defects are resolved.
- Test summary report is prepared and reviewed.
Test Deliverables
- Test Plan document
- Test cases and scripts
- Test data
- Test execution reports
- Defect logs
- Test summary report
Test Schedule
Activity |
Start Date |
End Date |
Owner |
Test Planning |
01/10/2025 |
01/20/2025 |
Test Manager |
Test Case Development |
01/21/2025 |
02/05/2025 |
Test Engineers |
Test Environment Setup |
01/21/2025 |
01/25/2025 |
Test Lead |
Test Execution |
02/06/2025 |
02/20/2025 |
Test Engineers |
Defect Resolution |
02/21/2025 |
03/05/2025 |
Developers |
Test Closure |
03/06/2025 |
03/10/2025 |
Test Manager |
Resources
- Personnel: Test Manager, Test Leads, Test Engineers, Developers, Business Analyst.
- Tools: Appium, JIRA, test devices (smartphones and tablets).
- Other: Test data, network configurations.
Roles and Responsibilities
Role |
Responsibility |
Test Manager |
Oversee the testing process, manage resources, and ensure adherence to the test plan |
Test Lead |
Coordinate testing activities and manage the test team |
Test Engineer |
Design and execute test cases, report defects |
Developer |
Fix defects and provide technical support |
Business Analyst |
Ensure test cases align with business requirements |
Defect Management
Defects will be managed through JIRA. The process includes:
- Logging defects with detailed information.
- Assigning defects to developers for resolution.
- Tracking the status of defects.
- Retesting resolved defects.
Risk Management
Potential risks and mitigation strategies:
- Device Compatibility Issues: Conduct extensive compatibility testing on various devices and OS versions.
- Performance Bottlenecks: Perform load testing and optimize the code.
- Security Vulnerabilities: Conduct thorough security testing and implement robust security measures.
Communication Plan
Communication Type |
Audience |
Frequency |
Medium |
Owner |
Status Report |
Project Team |
Weekly |
Email |
Test Manager |
Defect Review Meeting |
Key Stakeholders |
Bi-weekly |
Meeting |
Test Lead |
Test Summary Report |
All Stakeholders |
End of Testing Phase |
Document |
Test Manager |
Approval
- Prepared by: Mike Meier
- Email: matsuda3000@gmail.com
- Date: 01/20/2025
- Approved by: [Approver's Name]
- Date: [Approval Date]