System Test Plan
Table of Contents
- Introduction
- Objectives
- Scope
- Test Strategy
- Test Plan
- Test Schedule
- Resources
- Roles and Responsibilities
- Defect Management
- Risk Management
- Communication Plan
- Approval
Introduction
The purpose of this document is to outline the system test plan for the implementation of Two-Factor Authentication (2FA). This plan will detail the objectives, scope, strategy, schedule, resources, and procedures necessary to ensure thorough testing and successful deployment of 2FA in the system.
Objectives
The objective of the system testing for the 2FA implementation is to validate that the two-factor authentication functionality is working as intended, provides the expected level of security, and integrates seamlessly with existing system components.
Scope
The scope of the system testing includes:
- Verification of 2FA setup during the user registration process.
- Validation of the 2FA login process.
- Testing various authentication methods (e.g., SMS, email, authenticator apps).
- Ensuring 2FA works across different user roles and permissions.
- Validating the recovery process for lost or compromised 2FA methods.
- Performance and security testing of the 2FA implementation.
Test Strategy
The test strategy includes the following types of testing:
- Functional Testing: Verify the functionality of 2FA, including setup, login, and recovery processes.
- Performance Testing: Ensure the 2FA process does not degrade system performance.
- Security Testing: Validate that the 2FA provides the required level of security and that there are no vulnerabilities.
- Usability Testing: Ensure the 2FA process is user-friendly and does not hinder user experience.
Test Plan
Test Environment
The test environment will include:
- Hardware: Standard servers and workstations.
- Software: Operating systems, web browsers, and mobile devices.
- Network: Configuration mimicking the production environment.
- Tools: Testing tools such as Selenium, JMeter, and security testing tools.
Test Criteria
Entry Criteria:
- 2FA feature is fully developed and unit tested.
- Test environment is set up and configured.
- Test cases are reviewed and approved.
Exit Criteria:
- All test cases are executed.
- All critical and high severity defects are resolved.
- Test summary report is prepared and reviewed.
Test Deliverables
- Test Cases
- Test Scripts
- Test Data
- Test Execution Results
- Defect Logs
- Test Summary Report
Test Schedule
Activity |
Start Date |
End Date |
Test Planning |
12/19/2024 |
12/23/2024 |
Test Case Development |
12/24/2024 |
12/30/2024 |
Test Environment Setup |
12/24/2024 |
12/30/2024 |
Test Execution |
01/02/2025 |
01/15/2025 |
Defect Resolution |
01/16/2025 |
01/22/2025 |
Test Closure |
01/23/2025 |
01/24/2025 |
Resources
- Test Manager
- Test Lead
- Test Engineers
- Developers
- Business Analyst
- Testing Tools
Roles and Responsibilities
Role |
Responsibility |
Test Manager |
Oversee the testing process, manage resources, and ensure adherence to the test plan |
Test Lead |
Coordinate testing activities and manage the test team |
Test Engineer |
Design and execute test cases, report defects |
Developer |
Fix defects and provide technical support |
Business Analyst |
Ensure test cases align with business requirements |
Defect Management
Defects will be managed using a defect tracking tool. The process will include:
- Recording defects with detailed information.
- Prioritizing and assigning defects to responsible developers.
- Tracking the status of each defect.
- Verifying defect fixes and closing them once resolved.
Risk Management
Potential risks include:
- Delays in test environment setup.
- Unavailability of key resources.
- Integration issues with existing system components.
- Security vulnerabilities in 2FA implementation.
Mitigation strategies:
- Ensure early setup and configuration of the test environment.
- Maintain a resource backup plan.
- Conduct integration testing in parallel.
- Perform thorough security testing and code reviews.
Communication Plan
Communication Type |
Audience |
Frequency |
Medium |
Owner |
Status Report |
Project Team |
Weekly |
Email |
Test Manager |
Defect Review Meeting |
Key Stakeholders |
Bi-weekly |
Meeting |
Test Lead |
Test Summary Report |
All Stakeholders |
End of Testing Phase |
Document |
Test Manager |
Approval
- Prepared by: Bob Frapples
- Date: 12/19/2024
- Approved by: [Approver's Name]
- Date: [Approval Date]