System Test Plan

Table of Contents

  1. Introduction
  2. Objectives
  3. Scope
  4. Test Strategy
  5. Test Plan
  6. Test Schedule
  7. Resources
  8. Roles and Responsibilities
  9. Defect Management
  10. Risk Management
  11. Communication Plan
  12. Approval

Introduction

The purpose of this document is to outline the System Test Plan for the payroll project aimed at reducing manual work by integrating our HR system, HiBob, with the payroll software Pento. This integration will allow HiBob to feed employee information directly into the payroll platform, thereby minimizing manual data entry and reducing errors.

Objectives

The objectives of the system testing are:

  • To verify the integration between HiBob and Pento.
  • To ensure that HiBob acts as a single point of truth for all employee data.
  • To validate that manual administrative tasks are minimized.
  • To ensure that the payroll process is accurate and efficient.

Scope

The scope of the system testing includes:

  • Testing the data transfer from HiBob to Pento.
  • Verifying the accuracy of employee data (starters, leavers, salary changes, unpaid leave, maternity/paternity).
  • Testing additional payments (Gym, mobile phone duty) input.
  • Ensuring data integrity and correctness in the payroll process.
  • Functional, performance, and security testing of the integrated payroll system.

Test Strategy

The overall test strategy includes:

  • Functional Testing: To verify that the integration works as expected.
  • Performance Testing: To ensure that the system can handle the data load and perform efficiently.
  • Security Testing: To verify that the data transfer between HiBob and Pento is secure.

Test Plan

Test Environment

The test environment will include:

  • HiBob HR system
  • Pento payroll software
  • Necessary network configurations
  • Test data simulating real employee information

Test Criteria

  • Entry Criteria:
    • Test environment is set up and configured.
    • Test data is prepared.
    • HiBob and Pento systems are accessible.
  • Exit Criteria:
    • All planned tests are executed.
    • All critical and high-priority defects are resolved.
    • Test results are reviewed and approved.

Test Deliverables

  • Test cases
  • Test scripts
  • Test data
  • Test reports
  • Defect logs
  • Final test summary report

Test Schedule

Activity Start Date End Date Duration
Test Planning 01/22/2025 01/24/2025 3 days
Test Case Development 01/25/2025 01/28/2025 4 days
Test Environment Setup 01/29/2025 01/30/2025 2 days
Test Execution 01/31/2025 02/10/2025 11 days
Defect Resolution 02/11/2025 02/14/2025 4 days
Test Closure 02/15/2025 02/16/2025 2 days

Resources

  • Test Manager
  • Test Lead
  • Test Engineers
  • HiBob and Pento system access
  • Testing tools (e.g., test management software, defect tracking tool)

Roles and Responsibilities

Role Responsibility
Test Manager Oversee the testing process, manage resources, and ensure adherence to the test plan
Test Lead Coordinate testing activities and manage the test team
Test Engineer Design and execute test cases, report defects
Developer Fix defects and provide technical support
Business Analyst Ensure test cases align with business requirements

Defect Management

Defects will be recorded, tracked, and managed using a defect tracking tool. The process includes:

  • Logging defects with detailed information.
  • Prioritizing defects based on severity.
  • Assigning defects to respective developers for resolution.
  • Retesting resolved defects.
  • Closing defects once verified.

Risk Management

Potential risks and mitigation strategies include:

  • Integration Issues: Conduct thorough integration testing and have a rollback plan.
  • Data Accuracy: Validate data consistency between systems.
  • Performance Bottlenecks: Perform load testing to identify and address performance issues.

Communication Plan

Communication Type Audience Frequency Medium Owner
Status Report Project Team Weekly Email Test Manager
Defect Review Meeting Key Stakeholders Bi-weekly Meeting Test Lead
Test Summary Report All Stakeholders End of Testing Phase Document Test Manager

Approval

  • Prepared by: Wayne Sheridan
  • Email: wayne.sheridan@gmail.com
  • Date: 01/20/2025
  • Approved by: [Approver's Name]
  • Date: [Approval Date]